Ongoing
Projects


Solar power plant Marneuli
50 MW capacity
The total cost of the project - 30,000,000 USD
Project site - Marneuli (110 hectares)
Project completion time - 2024

Extension of 500 kV and 400 kV AC
Switchyards at Akhaltsikhe Converter
Station
Within the Open Program Extension Transmission Network
Georgia II, Energy Solutions, as a subcontractor, is carrying
out construction and installation works. Project completion
time - January 2027.

Construction of 220/110 kV Substation in Ozurgeti
Within the Open Program Extension Transmission Network
Georgia II, Energy Solutions, as a subcontractor, is carrying out construction and installation works. Project completion time - October 2026.

Bakhvi HPP Cascade Project Management
Installed capacity 46 MW
Project cost - 90,000,000 USD
Energy Solutions provides full project management of the Bakhvi HPP cascade in the Guria region, together with a US-based investment fund.
Project completion time - 2025
